Rooftop PV Sonyashnyk 2018

Description of the power plant

Rooftop solar power plant Rooftop PV Sonyashnyk 2018 is located in east part of Ukraine - Dniprovska city council, Dnipropetrovska region, Ukraine. The power plant is putted into operation on 2019 with installed capacity- 0.57 MW. Ltd "Sonyashnyk 2018" is a legal entity operating the power plant. It obtained the license for electricity generation on December 20, 2019 and permitted for the Feed-in-tariff in hryvnias equivalent of 16.37 eurocents starting from January 31, 2020.

LTD "SONYASHNYK 2018"

Putted into opperation

Dec 2019

Installed capacity

0.57 MW

DC

Feed-in-Tariff

16.37¢

Location

Dniprovska city council, Dnipropetrovska region, Ukraine

Key Indicators

10.0%

Capacity Factor

The unitless ratio of an actual electrical energy output over a given period of time to the maximum possible electrical energy output over that period.

0.568

Installed capacity

Installed capacity of the power plant (MW)

16.37

Tariff

Tariff established by NERC
(eurocents/KWh)


a share of power plants with lower indicator value among all RES
a share of power plants with lower indicator value among power plants of the same type

Contractors

Designer

LTD "HIPROPROM"

Additional information

In a paid subscription, you can additionally find answers to the following questions:

In addition, with a paid subscription, you can familiarize yourself with the available permits for Rooftop PV Sonyashnyk 2018

The presented list reflects the directions in which information on assets is collected. On the Rooftop PV Sonyashnyk 2018 some of this information may not yet be available, however, work is underway to collect the missing information and expand the amount of information provided to customers of a subscription.

Have ideas to improve energo.ua?

Energo.ua project is dedicated to add transparancy to Ukrainian renewable energy market.

In the system

1521

Assets

1332

Projects

4619

Companies

1A Sportyvna sq.,
Kyiv, 01001