Shyshatska HPP

Description of the power plant

Hydroelectric power plant Shyshatska HPP is located in east part of Ukraine - Shyshatskyi district, Poltavska region, Ukraine. The power plant is putted into operation on 2018 with installed capacity- 1.04 MW. Ltd "Budivelno-Transportna Kompaniya "Edelveys" is a legal entity operating the power plant. It obtained the license for electricity generation on October 22, 2009 and permitted for the Feed-in-tariff in hryvnias equivalent of 13.95 eurocents starting from November 01, 2009.

LTD "BUDIVELNO-TRANSPORTNA KOMPANIYA "EDELVEYS"

Putted into opperation

Aug 2018

Installed capacity

1.04 MW

Feed-in-Tariff

13.95¢

Location

Shyshatskyi district, Poltavska region, Ukraine

Key Indicators

31.0%

Capacity Factor

The unitless ratio of an actual electrical energy output over a given period of time to the maximum possible electrical energy output over that period.

1.038

Installed capacity

Installed capacity of the power plant (MW)

13.94

Tariff

Tariff established by NERC
(eurocents/KWh)


a share of power plants with lower indicator value among all RES
a share of power plants with lower indicator value among power plants of the same type

Contractors

Designer

LTD FIRMA NADAN

General contractor

LTD "HIDROINZHYNIRINH"

Additional information

In a paid subscription, you can additionally find answers to the following questions:

In addition, with a paid subscription, you can familiarize yourself with the available permits for Shyshatska HPP

The presented list reflects the directions in which information on assets is collected. On the Shyshatska HPP some of this information may not yet be available, however, work is underway to collect the missing information and expand the amount of information provided to customers of a subscription.

Have ideas to improve energo.ua?

Energo.ua project is dedicated to add transparancy to Ukrainian renewable energy market.

In the system

1521

Assets

1332

Projects

4619

Companies

1A Sportyvna sq.,
Kyiv, 01001