Description of the power plant
Ground-based solar power plant Tov Tatarbunary Solar 2 is located in south part of Ukraine - Bilhorod-Dnistrovskyi district, Odeska region, Ukraine. The power plant is putted into operation on 2019 with installed capacity- 9.98 MW. Ltd "Tatarbunary Solar 2" is a legal entity operating the power plant. It obtained the license for electricity generation on June 11, 2019 and permitted for the Feed-in-tariff in hryvnias equivalent of 15.03 eurocents starting from August 06, 2019.
Putted into opperation
Jul 2019
Installed capacity
9.98 MW
DCFeed-in-Tariff
15.03¢
+5% bonusLocation
Key Indicators
Capacity Factor
The unitless ratio of an actual electrical energy output over a given period of time to the maximum possible electrical energy output over that period.
Irradiation
Average annual sum of global irradiation per square meter received by the modules of the given system based on satellite data (kWh/m2)
Tariff
Tariff established by NERC taking into account the premium for the local component - 5%
(eurocents/KWh)
Contractors
Designer
LTD "PODILSKYY ENERHOKONSALTYNH"General contractor
LTD "NESS KONSTRAKSHN"Equipment
Type | Manufacturer | Model | ||
---|---|---|---|---|
KNESS | PVIS.1000 |
Additional information
In a paid subscription, you can additionally find answers to the following questions:
- What phone and email for contacts with Tov Tatarbunary Solar 2?
- What group of companies does the Tov Tatarbunary Solar 2 belong to?
- Who are the beneficial owners of Tov Tatarbunary Solar 2?
- What is the insolation at Tov Tatarbunary Solar 2?
- What is the current tariff in UAH for Tov Tatarbunary Solar 2?
- Is there a local component bonus for Tov Tatarbunary Solar 2 and what is its size
- What is the capacity factor of Tov Tatarbunary Solar 2?
- What is the monthly electricity production of Tov Tatarbunary Solar 2?
- What is the annual revenue of Tov Tatarbunary Solar 2?
- What market share does Tov Tatarbunary Solar 2 have in the Ukrainian renewable energy market in terms of capacity, production and revenue?
- What was the capital expenditure cost for Tov Tatarbunary Solar 2?
- Which company designed the project for Tov Tatarbunary Solar 2?
- Which company was the general contractor for Tov Tatarbunary Solar 2?
- What generating equipment (solar panels and inverters) is installed in Tov Tatarbunary Solar 2?
- What is the size of the land plot on which Tov Tatarbunary Solar 2 is located?
- What are the cadastral numbers of the parcels on which Tov Tatarbunary Solar 2 is located?
- What are the exact coordinates of the location of Tov Tatarbunary Solar 2?
- When were the grid connection specification forTov Tatarbunary Solar 2 issued and what capacity was approved in the specification?
In addition, with a paid subscription, you can familiarize yourself with the available permits for Tov Tatarbunary Solar 2
- Land allocation documentationTov Tatarbunary Solar 2
- Construction permits and declarative documentationTov Tatarbunary Solar 2
- Environmental Impact Assessment (EIA) DocumentsTov Tatarbunary Solar 2
- Feed-In-Tariff Setting DocumentsTov Tatarbunary Solar 2
The presented list reflects the directions in which information on assets is collected. On the Tov Tatarbunary Solar 2 some of this information may not yet be available, however, work is underway to collect the missing information and expand the amount of information provided to customers of a subscription.
Have ideas to improve energo.ua?
Energo.ua project is dedicated to add transparancy to Ukrainian renewable energy market.