Hydroelectric power plant Yablunytska HPP is located in west part of Ukraine - Putylskyi district, Chernivetska region, Ukraine. The power plant has installed capacity- 1.2 MW. Fea "Novosvit" is a legal entity operating the power plant. It obtained the license for electricity generation on October 16, 2002 and permitted for the Feed-in-tariff in hryvnias equivalent of 11.63 eurocents starting from October 08, 2009.

FEA "NOVOSVIT"

Putted into opperation

N/A

Installed capacity

1.2 MW

Feed-in-Tariff

11.63¢

Location

Putylskyi district, Chernivetska region, Ukraine

Key Indicators

19.0%

Capacity Factor

The unitless ratio of an actual electrical energy output over a given period of time to the maximum possible electrical energy output over that period.

1.2

Installed capacity

Installed capacity of the power plant (MW)

11.63

Tariff

Tariff established by NERC
(eurocents/KWh)


a share of power plants with lower indicator value among all RES
a share of power plants with lower indicator value among power plants of the same type

Contractors

Additional information

In a paid subscription, you can additionally find answers to the following questions:

In addition, with a paid subscription, you can familiarize yourself with the available permits for Yablunytska HPP

The presented list reflects the directions in which information on assets is collected. On the Yablunytska HPP some of this information may not yet be available, however, work is underway to collect the missing information and expand the amount of information provided to customers of a subscription.

Have ideas to improve energo.ua?

Energo.ua project is dedicated to add transparancy to Ukrainian renewable energy market.

In the system

1521

Assets

1332

Projects

4619

Companies

1A Sportyvna sq.,
Kyiv, 01001